Addis-Adama Expressway Hogs Funds
   
 
 
   
 
Addis-Adama Expressway Hogs Funds

The Ethiopian Roads Authority (ERA) is cutting one billion Birr from the budget of its other road construction projects to pay the advance needed for the construction of the six-lane expressway from Addis Abeba to Adama (Nazareth).

This followed a surprise request for an advance payment of 92 million dollars from each of the financers of the construction, Exim Bank of China and the government of Ethiopia.


The total budget for this road, scheduled to begin this fiscal year, is 612 million dollars, 349 million dollars of which will be obtained from the bank and the rest from the government.

The contractor, China Communications Construction Company (CCCC), needed to be paid an advance with far more than the 141.3 million Br which the Ministry of Finance and Economic Development (MoFED) had allocated.

This company had been active in Ethiopia through China Roads and Bridges Corporation (CRBC), which had been "serving as a flagship, a window, and a platform for [its] overseas operations," according to CRBC's website. CCCC has ranged among the top 500 global companies listed by the US-based magazine Forbes, since 2008.


"When we allocate funds at the beginning of the year, we always do it with an element of doubt," said a budget expert at the Ministry of Finance and Economic Development (MoFED), who requested anonymity because of possible complications related to the deduction of money from other projects. "Whether the financers release the money and the projects will be realised within the fiscal year."

"We set aside that sum for the sake of having some money on hand," he explained. "When the time comes, we are normally asked for a 15pc or 20pc advance payment."

ERA's budget for the fiscal year, contributed from the government, and through loans and grants amounted to 11.25 billion Br for over 200 projects. Now five million Birr to 10 million Br is being deducted from various projects to raise the one billion Birr that has been required for the advance.

ERA will ask for a bigger budget in order to avoid the disruption of projects which have lost part of their budgets for the expressway, an official of the authority, who also requested anonymity, said.


"If this company is related to CRBC, it is okay, because we are happy with CRBC. And if they get more money in advance, the job will also get done faster," said the ERA official.

The expressway will take a different route only 80Km long, 20Km shorter than the existing road from Addis Abeba to Adama. Hundreds of peasant families are expected to be affected by the construction, and their resettlement is expected to cost about 100 million dollars, according to the MoFED official. The construction is expected to begin in two months' time from both ends, and 20 million Br has been allocated for those farmers who will have to be relocated first.

"The construction will take two years," said the expert at MoFED. "We have prepared the relocation budget for each year."
 
 
 


Give your opinion on the Article

 

Please Register, you are currently just a guest here.
 
   
 
 
   
 
  • Addis Ababa-Adama expressway construction well in progress
  • Ethiopians are expected to buy decoder to watch ETV with 8 Channel
  • Parliament reviewing next year’s draft budget bill
  • Construction of Megenagna-Menelik Hospital, Kebena -Arat kilo roads to be c ...
  • ETHIOPIA: PM rejects Africa Avenue renovation costs as too high
  • Ethiopia signs $1.5b New Railway Study with 4 companys MoU
  • A Quarter of a billion Birr to be borrowed from the CBE
  • Ethiopia Undertaking 2.5 Billion Birr Water Projects: State Minister
  • Ethiopia Boost Budgt 39 Percent; Defense Gets Two Billion Birr Additional
  • Council of Ministers Approves $60m loan for Bole Road Constraction
  • EEPCO to start 7 wind, geothermal projects
  • Awash Construction sues Wegagen Bank for half a mln birr
  • Capital Starved DBE Gets 1.4b Br CBE Loan
  • Ministry says 15 per cent advance payment for Addis Ababa-Sebeta-Mesiso rai ...
  • Amhara Regional State District executes over 33m Birr development projects
  •  
       
     
     (Votes #: 0)
    Comments Print

    Discuss this article Here

    blog comments powered by Disqus
     
     
    Information
     
    Comment on the news site is possible only within (days) days from the date of publication.

     
     

     

     

     

     

     

    Home        |       Register        |       RSS        |       Privacy Policy        |       Sitemap        |       Contact Us


    DISCLAIMER

    The administrator of this site (newsdire.Com) cannot be held responsible for what its users post, or any other actions of its users. You may not use this site to distribute any material when you do not have the legal rights to do so. The contributor(s) and news providers are fully responsible for their content. In addition, the views and opinions expressed here are not necessarily those of the NewsDire. All services and information provided on this website are provided as general information only. It is your own responsibility to adhere to these terms.

    Copyright © 2008-2010 NewsDire. All rights reserved.